Design and Execution of Deviation Works on the Brașov – Târgu Mureș – Cluj – Oradea Highway

  • Braşov – Târgu Mureș – Cluj Slider1
  • Braşov – Târgu Mureș – Cluj Slider2
  • Braşov – Târgu Mureș – Cluj Slider3
  • Braşov – Târgu Mureș – Cluj Slider4
  • Braşov – Târgu Mureș – Cluj Slider5
    FACTS & FIGURES
    Client:

    Romanian National Company for Road Infrastructure Administration (CNAIR)

    Contractor:

    Özaltın-Ilgaz-Visio Joint Venture

    Location:

    Nădășelu, Mihaesti, Cluj-Napoca, ROMANIA

    Total Highway Length:

    5.5 km

    Platform Width:

    26 m (2x2 Highway)

    Pavement Type:

    Asphalt Pavement

    Number of Viaducts:

    2

    Total Viaducts Length:

    3,200 m

    Undertaken by the Özaltın-Ilgaz-Visio Joint Venture, this project covers a key section of the A3 Motorway, which extends across northwestern Romania. The works in the Nădășelu–Mihaesti section hold strategic importance within the Brașov – Târgu Mureș – Cluj – Oradea corridor of the A3 Motorway.

    With a design period of 9 months and a construction period of 18 months, the project’s first section includes a 1,214-meter bridge and a 780-meter road segment, while the second section comprises a 1,990-meter bridge and a 1,500-meter road segment. In the first section, a 266-meter portion of the bridge is designed as a balanced cantilever bridge.

    FACTS & FIGURES
    Client:

    Romanian National Company for Road Infrastructure Administration (CNAIR)

    Contractor:

    Özaltın-Ilgaz-Visio Joint Venture

    Location:

    Nădășelu, Mihaesti, Cluj-Napoca, ROMANIA

    Total Highway Length:

    5.5 km

    Platform Width:

    26 m (2x2 Highway)

    Pavement Type:

    Asphalt Pavement

    Number of Viaducts:

    2

    Total Viaducts Length:

    3,200 m