Transmission Line Between 400-kV Özlüce to Kiğı Basin Substation

  • 02
  • 03
  • DJI 20250107082908 0470 D
  • DJI 20250107083044 0475 D Enhanced NR
  • DJI 20250107090941 0503 D
  • DJI 20250107090952 0505 D
  • DJI 20250107104508 0507 D
  • DJI 20250107133635 0534 D
  • DJI 20250107140245 0558 D
  • DJI 20250107142616 0586 D
  • DJI 20250107150459 0596 D (Favori)
  • IMG 9610
  • IMG 9611
    FACTS & FIGURES
    Client:

    General Directorate of Turkish Electricity Transmission Corporation (TEİAŞ)

    Contractor:

    Özaltın Construction Co., Inc.

    Location:

    Bingöl, TÜRKİYE

    Length of the Line:

    36 km

    Number of Towers:

    93

    Status:

    In Operation

    The project consisted of route design, supply, wire pulling installation, tests and commissioning of a 170-kV high tension power line using a 1,272 MCM double circuit twin bundle conductor, which is spanning approximately 36 kilometers from the 400-kV Özlüce switchyard in Bingöl province, to Kiğı basin substation also located in the same province. 

    The project work also included the erection of 93 lattice foundations and galvanized steel towers. Furthermore, the scope involved stringing a total of a 200-kilometer optical ground wire (OPGW), an overhead static wire (OHSW), as well as an all-dielectric self-supporting (ADSS) cable.

    The project was delivered to ensure a secure, safe and reliable electrical infrastructure. It was completed on time and on budget in 2020, overcoming many challenges, including intense winter storms and high altitudes.

    FACTS & FIGURES
    Client:

    General Directorate of Turkish Electricity Transmission Corporation (TEİAŞ)

    Contractor:

    Özaltın Construction Co., Inc.

    Location:

    Bingöl, TÜRKİYE

    Length of the Line:

    36 km

    Number of Towers:

    93

    Status:

    In Operation