Upper Kaleköy Concession Project Profile

  • 01 Yukarikalekoy Hava 2019 0001
  • 02 Yukarikalekoy Hava 2019 0051
  • 03 Yukarikalekoy Hava 2019 0005
  • 04 Yukarikalekoy Hava 2019 0010
  • 05 Yukarikalekoy Hava 2019 0011
  • 06 Yukarikalekoy Hava 2019 0054
  • 07 Yukarikalekoy Hava 2019 0055
  • 08 Yukarikalekoy Hava 2019 0027
  • 09 Yukari Kalekoy Baraji Ve Hes (2)
  • 10 Yukari Kalekoy Baraji Ve Hes (3)
  • 11 Yukarikalekoy Hava 2019 0049
  • 12 Yukari Kalekoy Baraji Ve Hes (4)
  • 13 Yukari Kalekoy Baraji Ve Hes (5)
    FACTS & FIGURES
    Location:

    Bingöl, TÜRKİYE

    Investment Company:

    Kalehan Energy

    Shareholding:

    Özaltın İnşaat 50%; Cengiz İnşaat 50%

    Contract Model:

    Build-Operate-Transfer (BOT)

    Concession Period:

    49 Years

    Installed Capacity:

    626.85 MW

    Annual Power Generation:

    2.3 billion kWh

    Project Status:

    Operational

    Project’s Overview

    The Upper Kaleköy Dam and Hydroelectric Power Plant, also known as Yukarı Kaleköy, is located in Bingöl Province, eastern Türkiye, on the Murat River, a tributary of the Euphrates.

    Özaltın and Cengiz set up Kalehan Energy as a special purpose vehicle (SPV) for power generation, with each founder holding a 50% ownership interest. The SPV developed and implemented Upper Kaleköy as a greenfield project and now owns and operates the plant.

    Upper Kaleköy was the second project to be realized in Kalehan Energy’s hydropower cascade along the lower Murat River. The scheme was initially designed to comprise four projects with a combined installed capacity of 2,350 MW. Each project was structured on a finance–build–operate–transfer basis with a 49-year concession period.

    The Özaltın–Cengiz Joint Venture built the roller-compacted concrete dam and hydropower plant. The dam rises 137.50 meters above the riverbed and has a crest length of 566 meters. It impounds the Murat River to form a reservoir with a total storage capacity of 783.80 million cubic meters.

    The semi-underground powerhouse is configured to accommodate three vertical-axis turbine-generator units, each rated at 199.4 MW, and one smaller unit rated at 28.65 MW. The plant has a total installed capacity of 626.85 MW. Work on the project began in 2012. Construction was completed in February 2018, and the plant came online in April 2018.

    The plant supplies the national grid with an average annual output of 2.3 billion kWh of renewable electricity. According to the International Carbon Registry, the project’s annual greenhouse gas emissions reduction is estimated at 1.23 million tonnes of CO₂e.

    FACTS & FIGURES
    Location:

    Bingöl, TÜRKİYE

    Investment Company:

    Kalehan Energy

    Shareholding:

    Özaltın İnşaat 50%; Cengiz İnşaat 50%

    Contract Model:

    Build-Operate-Transfer (BOT)

    Concession Period:

    49 Years

    Installed Capacity:

    626.85 MW

    Annual Power Generation:

    2.3 billion kWh

    Project Status:

    Operational

    Kalehan Energy Group Logo

    Kalehan Energy

    Kalehan Enerji Grubu Eti Mahallesi, ATG Binası Ofis Katı, Celal Bayar Bulvarı No:78/225 06570 Ankara / Türkiye