Beyhan Dam and HEPP

  • Beyhan HES 002
  • Beyhan HES 004
  • Beyhan HES 010
  • Beyhan HES 011
  • Beyhan HES 017
  • Beyhan HES 020
  • Beyhan HES 022
  • Beyhan HES 023
  • Beyhan HES 024
  • Beyhan HES 025
  • Beyhan HES 035
  • Beyhan HES 036
  • Beyhan HES 039
  • Beyhan HES 040
  • Beyhan HES 042
  • Beyhan HES 043
  • Beyhan HES 045
  • Beyhan HES 047
  • Beyhan HES 048
  • Beyhan HES 049
  • 01 Beyhan Hava 2019 0001 (1)
  • 02 Beyhan Hava 2019 0036
  • 03 Beyhan Hava 2019 0008
  • 04 Beyhan Hava 2019 0011
  • 05 Beyhan Hava 2019 0017
  • 06 Beyhan Hava 2019 0101
  • 07 Beyhan Hava 2019 0102
  • 08 Beyhan Hava 2019 0013
  • 09 Beyhan Hava 2019 0050
  • 10 Beyhan Hava 2019 0014
  • 11 Beyhan 1 Baraji Ve Hes (8)
  • 12 Beyhan Hava 2019 0027
  • 13 Beyhan 1 Baraji Ve Hes (7)
  • 14 Beyhan 1 Baraji Ve Hes (5)
  • 15 Beyhan 1 Baraji Ve Hes (6)
  • 16 Beyhan 1 Baraji Ve Hes (2)
  • 17 Beyhan 1 Baraji Ve Hes (3)
  • 18 Beyhan 1 Baraji Ve Hes (4)
  • 19 Beyhan 1 Baraji Ve Hes
    FACTS & FIGURES
    Client:

    Kalehan Energy Company

    Location:

    Elazığ, TÜRKİYE

    Contractor:

    Özaltın-Cengiz Joint Venture

    Dam Type:

    Roller Compacted Concrete (RCC)-Gravity

    RCC Dam Volume:

    1,350,000 m3

    Height from Foundation:

    97 m

    Crest Length:

    521 m

    Installed Capacity:

    582.10 MW

    Annual Power Generation:

    1,6 GWh

    Project’s Overview

    The Beyhan Dam, with its hydroelectric power plant, is located on the Murat River, a tributary of the Euphrates in Elazığ province, Türkiye.
    The operation has involved the construction of a 1,350,000 m3 Roller-Compacted-Concrete (RCC) gravity dam with an integral water intake, and penstock encasement that have a conventional concrete volume of 101,000 m3. The dam is 97 meters tall from the foundation, and has a crest length of 521 meters, including an ogee spillway with a discharge capacity of 10,500 m3/s. An excess of 214,000 m3 of conventional concrete (CVC) was used to build the 3-bay spillway, which is furnished with 6 Tainter gates, on a solid foundation at the right abutment.

    The river diversion works comprised three tunnels with lengths of 535 meters, 572 meters and 582 meters, respectively. They were drilled, using the traditional method, through the left canyon of the river to a diameter of 11 meters. They were each concrete lined to a finished diameter of 9.5 meters.

    The construction also involved the foundation, the tailrace excavation, as well as river channel dredging, carried out for the power plant, which is positioned at the base of the dam. Nearly 228,000 m3 of concrete was poured from start-to-finish to erect the powerhouse. The plant houses four (4) vertical axis, Francis- turbine-generator units. While three (3) units are rated at 183.5 MW each, one small unit is rated at 31.6 MW. In unison these four units reach a power capacity of 582.10 MW.

    FACTS & FIGURES
    Client:

    Kalehan Energy Company

    Location:

    Elazığ, TÜRKİYE

    Contractor:

    Özaltın-Cengiz Joint Venture

    Dam Type:

    Roller Compacted Concrete (RCC)-Gravity

    RCC Dam Volume:

    1,350,000 m3

    Height from Foundation:

    97 m

    Crest Length:

    521 m

    Installed Capacity:

    582.10 MW

    Annual Power Generation:

    1,6 GWh